What this topic covers
Major Work Activity A of the RSOS Plumber 2023, common occupational skills, carries 14 of the 125 exam questions: task A-1, safety (3); task A-2, tools, access, rigging and hot work (3); task A-3, organizing work and documentation (3); task A-4, routine trade activities such as layout, supports, protection and commissioning (5). Task A-5, communication and mentoring, is not tested on the interprovincial exam. These are original practice notes, not Red Seal program documents. Code points are based on the National Plumbing Code of Canada 2020 (NPC 2020), the edition provided at the exam; trade points reflect standard methods and notions of the trade. The exam is open book, so the notes also say where to look in the code.
Site safety and PPE
- WHMIS 2015: the supplier provides the SDS; a workplace label goes on any container the product is transferred to. The gas cylinder pictogram marks gases under pressure (sub-task A-1.01 of the RSOS).
- Confined space: low oxygen means ventilate, retest, then enter under the permit; a purifying respirator adds no oxygen.
- Respirator: solvent cement vapours call for organic vapour cartridges; a dust mask only stops particles (sub-task A-1.02).
Lock-out/tag-out
- Sequence: isolate, lock and tag, dissipate residual energy such as trapped hydronic pressure, then verify that no energy remains (sub-task A-1.03).
- Personal lock: each exposed worker applies a lock; a tag alone does not stop a pump from being energized.
Tools, access, rigging and hot work
- GFCI: opens the circuit on leakage to ground, for corded tools in damp locations; a two-prong adapter removes the ground.
- Sling angle: tension per leg = (load / 2) / sin of the angle to the horizontal; 2400 lb. on two legs at 45 degrees gives about 1697 lb. per leg. The flatter the sling, the higher the tension (sub-task A-2.03). A designated signaler directs a blind lift.
- Cylinders: upright and secured, oxygen separated from fuel gas as the AHJ requires; a flashback arrestor stops a flame travelling back up the hose.
- Brazing or soldering: a filler melting above about 450 °C (840 °F) that flows by capillary action makes brazing; welding melts the base metal. Article 2.2.9.2. of the NPC 2020 caps lead in solders and fluxes for potable water at 0.2 %.
Drawings and organizing work
- Permit drawings: Article 2.2.2.1. of Division C lists the location and NPS of every building drain.
- RFI: a plan and specification conflict goes to the designer in writing. As-built drawings record what was built; shop drawings come before fabrication; an elevation view shows heights.
- Materials: cover plastic pipe with opaque material against UV and cap the ends; agree route changes with other trades.
Layout and pipe calculations
- Benchmark: a fixed point of known elevation for all levels.
- 45 degree offset: travel = set x 1.414 (set 300 mm gives 424 mm); at 45 degrees the run equals the set.
- Grade: grade = drop / run, so 12 m at 1 in 50 drops 240 mm.
- Cut length: centre-to-centre minus both end-to-centre dimensions plus both socket insertion depths. The formula sheet is provided at the exam.
Supports, protection and commissioning
- Spacing: Table 2.3.4.5. (Sentence 2.3.4.5.(2)) gives 1.2 m between horizontal supports for ABS or PVC pipe.
- Copper: hangers of other metals are insulated from copper tube (Article 2.3.4.3.).
- Sleeve: keeps a wall from bearing on the pipe (Article 2.3.5.2.); freezing protection is Article 2.3.5.3.
- Backfill: without manufacturer instructions, 300 mm of compacted backfill free of stones, cinders and frozen earth over the pipe (Clause 2.3.5.1.(1)(a)).
- Start-up: new potable piping is cleaned and flushed (Article 2.6.2.8.); one cold hydronic zone usually means trapped air. Fire stopping uses a complete listed system compatible with plastic pipe.
Sample questions (5)
1. Under WHMIS 2015, who provides the SDS when a contractor first buys a hazardous product such as thread sealant?
- The building inspector
- The delivery driver
- The product supplier
- The safety committee
Under WHMIS 2015 the supplier of a hazardous product provides the SDS to the purchaser, as described in sub-task A-1.01 of the RSOS. A building inspector enforces codes and does not issue product safety data. A delivery driver only transports the product, and a safety committee reviews site safety without preparing or supplying SDS.
2. Cutting oil is poured from a supplier drum into a small can that stays at the bench for the week. What must the can carry?
- A supplier label
- A TDG road placard
- A copy of the SDS
- A workplace label
When a hazardous product is transferred to another container that is kept at the workplace, WHMIS 2015 calls for a workplace label identifying the product and giving safe-handling information (sub-task A-1.01 of the RSOS). A supplier label is applied by the supplier to the original container. A TDG road placard relates to transport of dangerous goods, not to a bench can. The SDS must stay accessible to workers but does not replace the container label.
3. An atmosphere test inside a closed storage vault shows low oxygen, and a pipe must be installed inside. What is done first?
- Wear an air-purifying respirator inside.
- Ventilate the vault, then retest the air.
- Enter with an attendant standing outside.
- Limit each entry to a short time.
Low oxygen means the space is unsafe to enter, so the atmosphere is corrected by ventilating and then retested before a permit-based entry (confined space hazards, sub-task A-1.01 of the RSOS). An air-purifying respirator cleans the air but does not supply oxygen. An attendant outside is part of a proper entry but does not make the air breathable, and shorter entries do not remove the exposure.
4. A plumber applies solvent cement to ABS pipe in a poorly ventilated crawl space. Which respirator filter matches this hazard?
- A particulate filter alone
- A disposable dust mask
- An organic vapour cartridge
- An acid gas cartridge
Solvent cement gives off organic vapours, so the respirator needs organic vapour cartridges, chosen for the hazard and fitted correctly (sub-task A-1.02 of the RSOS). A particulate filter or a dust mask traps dust but not vapours. An acid gas cartridge is intended for acid gases rather than solvents.
5. The breaker of a hydronic circulating pump is locked and tagged, and its isolation valves are closed. What must be done before the pump flanges are opened?
- Bleed pressure and verify zero energy.
- Remove the lock briefly to test the motor.
- Add a second tag to the breaker door.
- Have the next shift confirm the lock.
A lock and tag isolate only the electrical source. The LOTO sequence also requires dissipating residual energy, such as trapped hydronic pressure, and then verifying that no energy remains (sub-task A-1.03 of the RSOS). Removing the lock to test the motor defeats the isolation. A second tag or a check by the next shift adds no verification of zero energy.