Major Work Activity D of the RSOS Plumber 2023, water service and distribution: 24 of the 125 questions. Task D-11 (water service) carries 6, Task D-12 (water distribution, including backflow prevention) carries 12 and Task D-13 (private water pressure systems) carries 6. These are original study notes for practice questions, not Red Seal program documents. Code points are based on the National Plumbing Code of Canada 2020, the edition handed out at the exam; other points are standard trade methods. Where to look in the code: Section 2.6 (water systems) and Article 2.3.7. for tests.

Water service pipe

Distribution system

Backflow prevention

Private water systems

Calculations

Take the free test · full question bank and mock exams with a subscription

Sample questions (5)

1. To what maximum static pressure at a fixture must a pressure-reducing valve limit the supply?

  1. 350 kPa
  2. 450 kPa
  3. 550 kPa
  4. 700 kPa

Article 2.6.3.3. of the NPC 2020 requires a pressure-reducing valve where the static pressure at any fixture may exceed 550 kPa, and the valve must limit the static pressure at the fixture to 550 kPa. The values of 350 kPa and 450 kPa are not Code limits for this rule, and 700 kPa is the air test pressure of Article 2.3.7.2., not a fixture limit.

2. An air pressure test at 700 kPa is read on a gauge marked in psi. What does the gauge read?

  1. 10.2 psi
  2. 101.5 psi
  3. 303.1 psi
  4. 4827.6 psi

The formula sheet converts kPa to psi by multiplying by 0.1450, so 700 x 0.1450 = 101.5 psi, which matches the air test of Article 2.3.7.2. of the NPC 2020. The value of 4827.6 psi divides instead of multiplying, 303.1 psi uses 0.433 psi/ft., a factor for feet of water head, and 10.2 psi shifts the decimal point.

3. A crew fills a new potable water service from a pond to pressure test it. What does the NPC require?

  1. Use potable water for the test.
  2. Strain the pond water first.
  3. Let the pond water settle first.
  4. Flush the pipe after the test.

Sentence 2.3.7.3.(2) of the NPC 2020 requires potable water to be used when a potable water system is tested. Straining or settling pond water removes particles but does not make it potable, and flushing the pipe after the test does not change the fact that non-potable water was used for the test.

4. A pipe maker states that an air test is not recommended for a new potable service. Which test is done?

  1. An air test at 700 kPa.
  2. An air test at 350 kPa.
  3. A visual check alone.
  4. A water pressure test.

Sentence 2.3.7.2.(2) of the NPC 2020 requires a water pressure test when the manufacturer states that an air test is not recommended. The 700 kPa air test of Sentence 2.3.7.2.(1) is the option the manufacturer excluded, a lower air pressure does not meet any Code value, and a visual check does not stress the piping.

5. Where is the accessible shut-off valve placed on a water service pipe entering a building?

  1. At the highest fixture.
  2. Close to the entry point.
  3. Beside the water heater.
  4. At the property line.

Sentence 2.6.1.3.(1) of the NPC 2020 requires an accessible shut-off valve located as close as possible to where the water service pipe enters the building. A valve at the highest fixture or beside the water heater isolates only part of the system, and a valve at the property line is not near the building entry.