Major Work Activity C of the RSOS Plumber 2023, sewers, sewage treatment and DWV systems, carries 32 of the 125 exam questions: task C-8, building sewers (7); task C-9, sewage treatment systems (5); task C-10, drainage, waste and vent systems (20). These are original practice notes, not Red Seal program documents. Code points are based on the National Plumbing Code of Canada 2020 (NPC 2020), the edition provided at the exam; trade points reflect standard methods and notions of the trade. The exam is open book, so the notes also say where to look in the code. Most rules sit in Sections 2.4 (drainage) and 2.5 (venting) of Division B.

Building sewer and private systems

Sizing drainage

Fittings and interceptors

Venting

Testing, service and calculations

Take the free test · full question bank and mock exams with a subscription

Sample questions (5)

1. Where does the building sewer of a house begin?

  1. At the base of the soil stack
  2. At a point 1 m outside the wall
  3. At the edge of the property
  4. At the public sewer main line

The definition in Article 1.4.1.2. of Division A of the NPC 2020 places the start of the building sewer where it joins the building drain, 1 m outside a wall of the building; from there it runs to the public sewer or to a private sewage disposal system. The base of the soil stack is inside the building, on the building drain. The edge of the property is only a point the sewer passes, and the public sewer main is where the building sewer ends, not where it begins.

2. A building sewer joins the public sewer downstream of the main cleanout. What is the minimum pipe size?

  1. NPS 2
  2. NPS 3
  3. NPS 4
  4. NPS 6

Article 2.4.9.4. of the NPC 2020 requires a building sewer connected to the public sewer downstream of the main cleanout to be at least NPS 4. NPS 2 and NPS 3 are smaller than the minimum. NPS 6 is acceptable, but it is a larger size than the minimum the Code asks for.

3. What is the NPC 2020 minimum slope for an NPS 3 drainage pipe, in millimetres of drop per metre of run?

  1. 10 mm per metre
  2. 20 mm per metre
  3. 40 mm per metre
  4. 50 mm per metre

Sentence 2.4.8.1.(1) of the NPC 2020 sets a minimum slope of 1 in 50 for drainage pipes of NPS 3 or less, which is 20 mm of drop for each metre of run. A drop of 10 mm per metre is 1 in 100, which is too flat. A drop of 40 mm per metre is 1 in 25 and 50 mm per metre is 1 in 20; both are steeper than the minimum, so neither is the minimum slope.

4. A building on a combined public sewer is being rebuilt. How must its new drainage piping be arranged?

  1. Separate drains joined inside the wall
  2. A single shared building drain
  3. One drain with a backwater valve
  4. Separate sanitary and storm drains

Sentence 2.1.2.1.(2) of the NPC 2020 does not permit a combined building drain, even where the public sewer is combined, so sanitary and storm piping are run as separate building drains. Joining the two drains inside the wall, sharing one drain, or adding a backwater valve to one shared drain all still create a combined building drain. Note A-2.1.2.1.(2) explains that some localities have accepted combined building drains on past performance, but a Note explains and does not change the requirement.

5. Row houses are built on separate lots beside one public sewer. How are their building sewers connected?

  1. Each building has its own connection.
  2. The whole row shares one connection.
  3. Pairs of houses share a connection.
  4. Middle units tie into end units.

Article 2.1.2.4. of the NPC 2020 says piping in a building connected to public services is connected separately from the piping of any other building. Sharing one connection among all houses or among pairs breaks this rule, and middle units cannot tie into end units. The exception is an ancillary building on the same property, such as a garage, which may use the same service.